  • Objective

    To enhance the safety of NH-163 (Warangal-Mulugu Road) through the installation of 15,000 metres of W Beam Metal Crash Barriers. The goal was to ensure timely delivery and installation of the barriers within a 21-day period, maintaining high-quality standards and full compliance with safety regulations.

  • animation-w4Challenges

    • Tight Timeline: The project required the delivery and installation of 15,000 metres of W Beam Metal Crash Barriers within just 21 days.
    • Logistics and On-time Delivery: Coordinating timely delivery of materials and installation across the highway project to meet the 21-day deadline.
    • Quality Assurance: Ensuring all materials met required quality standards while adhering to the strict project timeline.
    • Documentation and Compliance: Providing necessary Material Test Certificates (MTC) with each delivery, ensuring all materials complied with safety and regulatory standards.

  • Solutions

    • Timely Delivery and Installation: Through precise planning and coordination, all 15,000 metres of W Beam SSSB were delivered and installed on schedule, within the 21-day timeframe.
    • Quality Assurance: Rigorous quality control was applied at every stage to ensure that the W Beam barriers met the necessary safety, structural, and regulatory standards.
    • MTC and Documentation: Detailed Material Test Certificates (MTC) were provided with every shipment, ensuring full transparency and compliance with the project’s specifications.
    • Efficient Logistics: Coordinated transportation and installation logistics to ensure that all materials reached the site on time and installation was completed without delays.

  • animation-w4Conclution

    The successful delivery and installation of 15,000 metres of W Beam Metal Crash Barriers for the widening and strengthening of NH-163 (Warangal-Mulugu Road) exemplified our ability to meet challenging timelines while maintaining the highest quality standards. The project was completed within the 21-day deadline, enhancing road safety on NH-163. This success reinforces our commitment to delivering reliable, high-quality safety solutions, on time, and to the satisfaction of our clients.