Electricity Company of Ghana Ltd Project

  • Objective

    To enhance Ghana’s electrical infrastructure, this project focused on supplying 10 MTRS octagonal poles for the Electricity Company of Ghana Ltd. The aim was to ensure reliable power distribution with timely delivery and high-quality standards.

  • animation-w4Challenges

    The project required the production of 5908 octagonal poles using a special grade of imported raw materials (MC500 steel), adhering to approved drawings and technical data sheets. The client’s stringent quality assurance process, including process inspections, type testing, and final inspections by the engineers of the Ghana Electricity Authority, added to the complexity. Meeting the tight deadlines required efficient coordination.

  • Solutions

    Utkarsh India produced the poles across two production units, leveraging state-of-the-art facilities to ensure compliance with the client’s specifications. The production process included:

    • Use of MC500 steel for durability and strength.
    • Process inspections by the client’s QC engineers at multiple stages.
    • Comprehensive type testing and final inspections by Ghana Electricity Authority engineers.
    The materials were delivered from both production plants on a war footing basis, ensuring all deadlines were met without compromising quality.

  • animation-w4Conclution

    Utkarsh India successfully delivered 5908 octagonal poles within the stipulated time frame, contributing to the Electricity Company of Ghana’s infrastructure goals. By combining advanced engineering, stringent quality control, and efficient logistics, we reaffirmed our commitment to excellence and timely execution in international projects.