Tata Power Solar Systems Limited

  • Objective

    The project aimed to install a Carport Solar Structure at Maruti Suzuki’s facility in Sonipat, facilitating solar power generation, utilization, and EV charging infrastructure. This initiative was part of a sustainable energy transition, integrating renewable energy solutions with vehicle charging stations.

  • animation-w4Challenges

    The project posed key challenges, including:

    • Strict delivery timelines, requiring the supply and installation of 1,742 MT of solar structures within 60 days.
    • Ensuring compliance with technical specifications, using HR Coil and Zam-coated materials.
    • Coordinating logistics, ensuring timely delivery, quality assurance, and Material Test Certificates (MTC) along with the vehicle.

  • Solutions

    Utkarsh India successfully addressed these challenges by:

    • Precision Manufacturing: Designed and fabricated 2mm thickness Carport Solar Structures (Column Post Clip) for optimised load-bearing and durability.
    • Efficient Logistics & Delivery Management: Streamlined production and dispatch operations to meet the strict 60-day deadline.
    • Quality Assurance & Compliance: Conducted rigorous quality inspections at every stage to ensure technical accuracy and durability.
    • Manpower Allocation: Deployed a skilled workforce to ensure seamless execution and timely installation.

  • animation-w4Conclution

    Utkarsh India played a crucial role in supporting Tata Power Solar Systems Limited’s renewable energy mission by delivering high-quality solar structures on time. This project strengthens the integration of solar power with EV infrastructure, reinforcing our commitment to sustainable and efficient energy solutions.