Mega Lift Irrigation Project
-
Objective
The objective of this project was to supply 400 MT of HDPE pipes with copper tracer for the Mega Lift Irrigation Project in Anandapur, Odisha. The main goal was to improve flood management and enhance irrigation efficiency in the region. The challenge was to meet the delivery deadline of 60 days while incorporating a new requirement: the supply of HDPE pipes with copper tracer, which had not been supplied previously.
-
Challenges
- New Requirement for Copper Tracer: For the first time, HDPE pipes with copper tracer were required for the project, which added complexity to the manufacturing process. This new specification demanded careful coordination and adaptation.
- Strict Timeline: The project had to be completed within a 60-day period, which required meticulous planning and fast execution to meet the delivery requirements without compromising quality.
- Logistics Coordination: Timely transportation of 400 MT of HDPE pipes to the project site in Anandapur, Odisha, was a major challenge due to the large volume of materials and the remote location of the project area.
-
Solutions
- Collaborative Planning: After extensive discussions with the plant, purchase team, and logistics department, a detailed plan was put in place to ensure timely manufacturing and delivery. Close coordination helped manage production schedules and resource allocation efficiently.
- Efficient Execution: By aligning the production and logistics teams, we ensured the supply of 400 MT of HDPE PE 100 PN 6 pipes with copper tracer, meeting the technical requirements while also adhering to the 60-day deadline.
- Logistical Support: The logistics team ensured that the pipes were transported smoothly to Anandapur, overcoming any challenges posed by distance or infrastructure, ensuring timely delivery to the project site.
-
Conclution
The successful supply of HDPE pipes with copper tracer for the Mega Lift Irrigation Project, within the 60-day period, highlights LCC Projects Pvt Ltd’s efficiency in handling new challenges, such as the introduction of copper tracer, while maintaining high standards of quality and meeting tight deadlines. This project underscores our commitment to providing innovative solutions that contribute to better flood management and efficient irrigation systems in rural areas.